Of all provinces, autonomous regions and municipalities directly under the Department of housing and urban construction (Municipal Committee, City Garden Committee, urban and rural construction and Transportation Commission, the municipal development and Reform Commission) (economic and Trade Commission, the Commission by letter), the Xinjiang production and construction corps construction bureau, development and Reform commission:
In accordance with the "State Council on Further Strengthening the efforts to achieve the" Notice of 11th Five-Year "energy-saving emission reduction targets" (the [2010]12) requirements, December 2010, the Ministry of housing and urban construction, the national development and Reform Commission jointly on the 30 municipalities, the provincial capital city, plans to municipalities and 20 other city lighting energy saving work the special supervision and inspection. Are notified as follows:
First, the basic situation of inspection
In this survey, field sampling of 50 city 280 lighting projects (road lighting landscape lighting project 146, project 134), of which 27 projects and 32 road lighting landscape lighting project was carried out on-site inspection. Overall, city lighting standard and high energy consumption phenomenon has been effectively controlled, the completion of the "Middle East" in 11th Five-Year to determine energy-saving emission reduction targets and conditions of the western region city road lighting out inefficient lighting products task.
(a) urban road lighting electricity saving achieved remarkable results
According to the statistics from 2005 to 2010 the city of lights, electricity and lights installed total power of the city road lighting unit power consumption decreased year by year, "11th Five-Year" during the annual decline of 3%, accumulative total 14.6%. accumulated power saving 25% city inspection during the "11th Five-Year" City: Rizhao City, Liuzhou City, Zunyi City, Benxi city and Changchun city.
(two) the urban road lighting above the branch basically eliminated the inefficient lighting products
Urban road lighting has been basically eliminated the inefficient lighting products. Basically achieved the "11th Five-Year" energy saving and emission reduction targets.
(three) the operation and management level of energy saving in urban lighting facilities has been continuously improved
Most cities can be in accordance with the "urban road lighting design standards" and the principle of the use of savings, the use of street light monitoring system to take the "midnight light" mode, through time-sharing control to achieve energy saving. Kunming city and Ji'nan city for the transformation of street lighting control system, Tianjin City, Kunming City, Qingdao City, Sanya City, Wuhan City, Nanchang City, Hefei city has also established a centralized control system of city landscape lighting.
Two, check the problems found
(a) urban lighting special planning work needs to be strengthened
The inspection found, Urumqi, Harbin, Shenyang, Hohhot, Changchun, Nanchang, Zhengzhou and other 7 provincial capital city and Jiamusi, Benxi, Wulanchabu, Changzhi, Pingxiang, Shiyan, Xinxiang and other 7 city without preparation of city lighting special planning; lack of energy-saving lighting requirements of city lighting special planning of Ji'nan City, Tonghua City and Rizhao City the measures and.
(two) high energy consuming lighting facilities still exist
Inspection found that the city of Sanya, Harbin, Guangzhou city landscape lighting is also the use of powerful searchlights and high-power light projection. Tianjin, Shijiazhuang, Dalian, Shenyang, Harbin, Hohhot, Changchun, Fuzhou, Guiyang, Yinchuan, Zunyi, Tonghua, Jiamusi, Wulanchabu, Baoji, Xinxiang 16 City Lane in the city, not out of large area light source control device in low lighting. The branch of Shanghai city road lighting lamp has more than 6 thousand inefficient lighting products more than and 60 lamp mercury lamp, inefficient lighting products still exist the following branch lamp lighting roads in the city of Zhongshan, there are still the following incandescent lighting branch roads in the city of Jiamusi.
(three) the lack of effective supervision of urban lighting construction
Inspection found that the city lighting project design part of the city without professional demonstration, not strict; some projects change the design in the construction stage, the impact of energy standards; part of city lighting project is not according to the provisions of the special approval delivery management operation management part of the project, the need for two to transform to achieve energy-saving lighting requirements, resulting in a waste of. Some city lighting project supervision, luminance (illuminance) value or the unit area of the lighting installation power does not comply with the provisions of existing standards, such as: Xi'an North Street, Gulou road lighting project landscape lighting project and Sanya City Pro spring bridge road lighting project.
Throughout the country in accordance with the overall arrangements for energy saving and emission reduction, and earnestly fulfill their responsibilities, strengthen the management of urban lighting energy conservation. Provincial housing and urban construction administrative departments in the inspection report issues, jointly with the competent departments at the same level of energy-saving rectification, supervise the city rectification, and in accordance with the "City Lighting Management Regulations" and other relevant provisions shall be dealt with. Ministry of housing and urban construction will be in 2011 in the field of urban and rural construction of energy-saving emission reduction special supervision and inspection.
The inspection of the city in 2010 to complete the work of urban lighting energy conservation inspection results see Annex 1, 2
Annex: 1.30 municipalities, provincial capitals, cities in 2010 the results of urban lighting energy conservation inspection
2.20 other cities in 2010 the city lighting energy saving work inspection results
Ministry of housing and urban rural development of People's Republic of China
General Office of the State Development and Reform Commission
Two, March 14th
Annex 1:
30 municipalities, provincial capitals, cities in 2010, the city's energy saving inspection work
Contact: mack
Phone: 13332979793
E-mail: mack@archled.net
Add: 3rd Floor, Building A, Mingjinhai Second Industrial Zone, Shiyan Street, Baoan, Shenzhen,Guangdong,China